Market Demand Survey

COMMENCEMENT OF THE INCREMENTAL CAPACITY PROCESS PURSUANT TO THE REGULATION (EU) NO. 2017/459 ON ESTABLISHING A NETWORK CODE ON CAPACITY ALLOCATION MECHANISMS IN GAS TRANSMISSION SYSTEMS

Plinacro announces to the interested public that on 5 July 2021 it commenced the incremental capacity process in compliance with chapter V of the Regulation (EU) no. 2017/459 of 16 March 2017, for the incremental capacity:
  1. at the existing interconnection points;
  2. by establishing a new interconnection point;
  3. for the reverse flow on the interconnection point at which the capacity was previously offered in one direction only.
In cooperation with the neighbouring transmission system operators Plinacro will conduct an assessment of market demand for incremental capacity.

Plinacro´s assessment of the non-binding requests for the firm capacity will be carried out in the period from 5 July to 30 August 2021.
For more additional information and a questionnaire for the assessment of the non-binding demand for the firm capacity on the interconnections see the following links:

Instructions for completing the form 

Form for submitting non-binding demand indicators 

Participants are reminded that a non-binding request for the firm capacity on the interconnection must be submitted to both neighbouring transmission system operators. 

If two entities plan to submit a request jointly, one on the one side and the other one on the other side of the interconnection point, then the interest should be expressed in a joint request with both neighbouring operators at the interconnection point.

Please be so kind to send any additional questions you may have regarding the incremental capacity process as well as completed tables to the e-mail address market@plinacro.hr by 30 August 2021, at the latest.

Within 8 weeks after the market test, at the latest at 25.10.2021. Plinacro will publish the demand assessment report.
 
Previous topic:
Market Demand Survey